UPDATE
·         The contractor is currently prepping the ground at the bottom of the canyon for the temporary asphalt, which will be installed in the latter part of this week.
·         Both lanes of traffic through the canyon will be opening to the public on Saturday, December 22nd, to allow for safe and convenient holiday travel.  One lane travel will resume on January 2, 2013.
Thank you all for your patience during this project.  Your feedback is very much appreciated.  Feel free to visit the website at www.ogdencanyonh2o.com, or call the hotline at (801) 675-8198.  You may also stop in to speak with us at the project hub located at the Horrocks Engineers office at 3544 Lincoln Avenue, Suite 11, in Ogden.