First, SR-39 in Ogden Canyon will be closed to all through traffic tonight beginning at 10:00pm until 6:00am Saturday morning, and again on Saturday night, beginning at 10:00pm until 6:00am on Sunday
morning, in order to install permanent
asphalt in the fourth (and final) phase of construction. During the
hours listed above, all Canyon residents living west of Phase 4
(approximate address: 600 Ogden Canyon) can access their homes from the
west (bottom of the canyon). All canyon residents
living in the fourth phase of construction will be able to access their
homes during the closure, but there may be longer than usual delays
because of the location of the large equipment. Please keep this in
mind as you plan your evening travels.
Also, there were some issues encountered during the
last few days stemming in large part from the high demand related to
the unseasonably high temperatures. As such, the upper (and final)
connection was not completed during the roaming
shutdowns. Because of the issues the contractor has encountered lately
with the temporary water, we would like to complete this connection
sooner, rather than later. In order to complete this connection,
another water shutoff will be necessary. This temporary
water shutoff will only impact those residents living in the third and
fourth phases of construction, and is scheduled for Sunday night, beginning at 9:00pm and will be in effect for approximately 8 hours. Water should be restored by 5:00am on Monday
morning.
If your water is not restored by then, please let us know so that we
can resolve any issues quickly. This will be the final shutoff of the
entire project.
Also on Sunday
night, the contractor will move the traffic control back down to the
mouth of the canyon to begin removing the old temporary asphalt section
and replacing it with 8 inches of permanent asphalt. The contractor
anticipates
that approximately 2,500 lineal feet of asphalt will be removed and
replaced before the 4th of July weekend. The rest will be completed after the 4th of July weekend.
Lastly, beginning at 5:00am on July 4th,
the traffic control will be removed and both lanes of traffic will be
open to accommodate holiday travel. Both lanes will remain open until
9:00pm on July 7th, at which time
the lane restrictions and delays will resume.
Thank you for taking the time to read through this
update. If you have any questions or concerns about this closure or any
other aspect of the project, please let me know.
Best regards,
HORROCKS ENGINEERS